Exam : ASC-012
Title
:
A
S
C High Availablity
Assessment
Version : Demo
1 / 2
The safer , easier way to help you pass any IT exams.
1.In a 2-node 5.1 Replicated Data Cluster using VVR, which option should be discussed with the
customer?
A. setting the AutoFailover service group attribute to 2
B. using SystemZones for the service groups
C. setting the ClusterFailOverPolicy service group attribute to Manual
D. using Hybrid service groups for the replication service group
Answer: A
2.A customer has a large high-availability environment comprising of 90 Veritas Cluster Server (VCS)
clusters across 3 sites. Thier business continuity group requires a monthly set of reports showing the
availability and downtime for each service that is clustered. What solution should you recommend?
A. Storage Foundation Manager
B. Veritas Operations Manager
C. Global Cluster Manager
D. VCS webGUI
Answer: B
3.Which two should be captured in the Symantec Design Report Questionnaire for a VCS or SF/HA
Implementation Service? (Select two.)
A.Prerequisites for implementing VCS
B.Details of the physical environment, including details of the servers, O/S networks and storage that will
be deployed in the solution
C.List of VCS agents that will be deployed in the solution, including requirements for custom agents
where applicable
D.List of the service groups, resources and dependencies that are to be configured in the solution
E.Details of the applications to be clustered, including service level objectives
Answer: Pending
4.What are the recommended project phases for VCS or SF/HA Implementation Services, in the right
order?
A. Assess, Design, Transform, Operate (ADTO)
B. Design, Installation, Configuration, Testing, Project Close
C. Planning and Design, Installation and Configuration, Testing, Project handover and close
D. Project Initiation and Planning, Design, Implementation and Testing, Operations Handover, Project
Close
Answer: D
5.Which of the following tools should you primarily use to perform pre-installation checks for implementing
VCS or SF/HA 5.1?
A. Common Product Installer (CPI)
B. SORT Installation and Upgrade Assessment
C. VRTS Explorer
D. VCS Configuration Wizard
Answer: B