Consulting approaches to process improvement Boston Consulting Group

0.00 (0 votes)
Document Description
The BCG has a background in strategy consulting and considers itself as a major contributor to the strategy field. Several of the concepts being developed by BCG have, in fact, found their way into the general method portfolio of strategy development and strategic change. The most prominent one is the Boston Matrix (Boston Square), a qualitative technique for product life-cycle and product portfolio analysis. The BCG employs a set of twelve guiding principles for reengineering. Even though they can not be considered as a formal method, they provide a basis for the analysis and design work being part of a process improvement initiative. The BCG approach has a clear focus on process cycle-time and has been promoted under the name of Time Based Competition. The publication of a book under the name of Competing against Time: How time-based competition is reshaping global markets, authored by BCG consultants George Stalk and Thomas Hout (1990), has been contributing to making BCG a player in the arena.
File Details
Submitter
  • Name: oscar
Embed Code:

Add New Comment




Related Documents

Consulting approaches to process improvement Boston Consulting Group

by: samanta, 11 pages

The BCG has a background in strategy consulting and considers itself as a major contributor to the strategy field. Several of the concepts being developed by BCG have, in fact, found their way into ...

Boston Consulting Group (BCG) Growth-Share Matrix User Guide

by: samanta, 5 pages

In the early 1970’s the Boston Consulting Group (BCG) developed a model for managing a portfolio of different strategic business units (SBUs) or major product lines. The BCG Growth-Share ...

Karnatik Consulting Group

by: SR, 4 pages

Karnatik Consulting Group, Brochure 2012-2013.

BOSTON CONSULTING GROUP MATRIX ( BCG )

by: samanta, 25 pages

This technique is particularly useful for multi-divisional or multi-product companies. The divisions or products compromise the organisations “business portfolio”. The composition ...

Basic Tools for Process Improvement

by: shinta, 25 pages

A Pareto Chart is “a series of bars whose heights reflect the frequency or impact of problems. The bars are arranged in descending order of height from left to right. This means the ...

The Boston Consulting Group Project Team Muzaffer Egeli Alp Borak ...

by: etoile, 7 pages

Due to the current efforts of Turkey trying to become a member of EU, the recent global scandals of large corporates in the most developed markets of the world, the competition of emerging markets to ...

Continuous Process Improvement & Kaizen Events

by: monkey, 2 pages

Continuous Improvement (Kaizen) is both a mind-set and a range of techniques to review and evaluate work processes. As a mind-set, it is a way of approaching work so that involvement

Generic Process Transformation Model: Transition to Process- based ...

by: imogen, 16 pages

The competitive global market climate of the new millennium has raised awareness of business processes as the most important management paradigm (Levi, 2002). Consequently, process elements, as well ...

Develop photographic memory to process your tasks like a high speed computer (Mental Photography is your Birthright)

by: praveenben, 28 pages

For More Useful Information on Develop photographic memory to process your tasks like a high speed computer Visit: http://praveenben.com - You were born with a photographic memory.Some people carry ...

“Neural Networks with Self-Organizing Maps applied to Process Control”

by: vane, 14 pages

“Neural Networks with Self-Organizing Maps applied to Process Control” (1) Juan Cevallos Ampuero ABSTRACT This research allowed to compare the Artificial Neural Networks ANN process ...

Content Preview
Consulting approaches to process improvement
Boston Consulting Group

Kai A. Simon

Viktoria Institute
Author’s Note: This is a part of an early draft of my doctoral dissertation that was
shortened considerably for the final version. Nevertheless, it might be a useful
collection of insight for organizations that face a need for redesigning their business
processes and wish to learn more about the basic concept and how some major
consulting firms approach it methodologically. The series consists of 7 parts –
Introduction, descriptions of the methodologies of Andersen Consulting, Bain, BCG
and McKinsey, a high level comparison, and some guidelines or selecting consultants.
Boston Consulting Group (BCG)
The BCG has a background in strategy consulting and considers itself as a major contributor
to the strategy field. Several of the concepts being developed by BCG have, in fact, found
their way into the general method portfolio of strategy development and strategic change.
The most prominent one is the Boston Matrix (Boston Square), a qualitative technique for
product life-cycle and product portfolio analysis.
The BCG employs a set of twelve guiding principles for reengineering. Even though they can
not be considered as a formal method, they provide a basis for the analysis and design work
being part of a process improvement initiative. The BCG approach has a clear focus on
process cycle-time and has been promoted under the name of Time Based Competition. The
publication of a book under the name of Competing against Time: How time-based
competition is reshaping global markets, authored by BCG consultants George Stalk and
Thomas Hout (1990), has been contributing to making BCG a player in the arena.
According to the principles of the BCG approach, time is the most important aspect of
process improvement and constitutes a prerequisite and driver for improvements in other
performance dimensions, such as cost and quality. The relation between the different
dimensions can be described like following.
1

Decreased cycle
time
Reduced
Increased
Improved
costs
variety and
quality
- materials
flexibility
- initial delivery
- labor
- offer various
- long term
- overhead
product types
- problem
- corporate
- expand offerings
resolution
overhead
more frequently
- customer service
Increased
Accelerated
Greater
profits
growth
share
Change basis of competition
- increased value -> differentiation
- build barriers
- achieve worldwide competitiveness

Figure: Time as primary improvement factor
The role of IT
The Boston Consulting Group does not offer IT products or services. Despite this fact,
information technology is considered an important tool for reengineering efforts, if it is linked
to business and organization strategy. Additionally, the positive impact of IT is linked to the
requirement of customer value creation. In this area, BCG does not offer systems
development assistance, but strategic guidance. IT development is done in-house by clients,
or outsourced to specialized firms. However, as a result of the increasing importance of IT,
e.g. e-commerce, BCG has rethought its own strategy and is now offering some IT services
in the area of Web-site prototyping.
Information technology is considered as being value-adding, if it increases speed and
accuracy to reduce cost, which often is achieved when whole functions or activities can be
reduced or eliminated with the help of IT, or when core competencies are developed, i.e. that
new strategic business opportunities are deployed, that have not been exploited by the
company or any competitor. A third area for IT use is the support of information-rich
processes, where IT can provide help in managing large amounts of information efficiently.
2

Using information technology for achieving competitive advantage includes a genuine
understanding of how it can be deployed, and when this should be done, where the ”how”
question is answered by line managers together with IT experts, and the ”when” question by
top management, which has to plan and guide the implementation according to the firm’s
strategic objectives.
The twelve principles of reengineering
BCG is using a set of 12 principles that are used as guiding principles, rather than
imperatives for the change process. Taking its starting point in the role of senior
management and strategy, these guidelines basically describe the critical success factors for
a reengineering project. The following list summarizes the BCG principles and provides a
short interpretation of their meaning.
Senior management must lead reengineering. This means firstly, that senior
management's role is to lead the change, but not to manage it. It is important to
distinguish between these roles, where leading means facilitating, promoting and
sponsoring, whereas managing means control and direct intervention. Secondly, senior
management is responsible for "shaking the barrier", i.e. removing road-blocks set up
within the organization by people opposing the change process.
Strategy must drive reengineering. The foremost strategic objective is to create
competitive advantage. However, competitive advantage is not solely depending from
company internal structures and processes, but is basically created through delivering
service to customers. Consequently, the underlying strategy supporting the reengineering
effort must take into consideration external effects. In addition, strategy must be balanced
again operational improvement, i.e. changing the strategic direction must even result in
sustainable bottom-line improvements.
Add value for customer. BCG has the thumb rule, that for every dollar in margin
improvements through cost reduction, at least two dollars can be added as increased
customer value. This aspect clearly points out the difference between reengineering and
cost-cutting approaches, which have been running under the label. Cost-cutting, or
downsizing, is a means for improved efficiency, but does not necessarily elevate
effectiveness.
Focus on process, not function. The change team should contain people from all parts
of the organization being concerned. However, it must be clear that the participation in
the change team does not mean to represent a certain function and to serve as a sentry
for its interests. Instead, all members of the team need to focus on the targeted
3

processes. Also, people participating in a change team should be chosen upon their
openness to radical change and ability to think "out-of-the-box".
Play to win. Reengineering is not a ”do it in your spare time” job. It is necessary to
assign the best available people to the project. Additionally, there must be clear
incentives for participation in the effort, i.e. that career opportunities must exist for those
who are dedicating themselves to the project.
Take a system view. Processes need to be considered from an end-to-end perspective,
i.e. that they are looked upon from customer need to the satisfaction of the need. The
customer thus plays a double role in being the determining factor for the design of the
process, as well as its customer. This view is substantially different from the means-end
analysis often used in traditional change projects, where customers are considered as
the receiver of the outcome of a push-process.
Preplan and learn as you go. It is necessary to stake out the over-all direction of the
project, but it could be fatal to create a route description, since it must be possible to
make adjustments during the change process. This also means that a process view is
taken at the change effort.
No ”one size fits all”. There is no one best way to handle any occurring situation. This
means that different approaches are required and that action being taken throughout the
process is situated, rather than pre-determined. It also requires that metrics for
performance measurement must be chosen accordingly, i.e. that simple quantity
measures often are inadequate as for example when looking at knowledge intensive
work, such as R&D.
Metrics matter. Customer often perceive a firm in a way that differs significantly from the
way the firm looks at itself. Therefore, a company should use the same measure as their
customers in order to create a common ground for measuring and evaluating
performance.
Care for the human dimension. Reengineering success stands and falls with the
people in the organization. It is therefore imperative to understand and anticipate
individuals’ expectations, emotions, and behavior. This includes to manage fear and
resistance to change. This aspect is also the one being most frequently neglected.
Reengineering is not a one-time thing. Reengineering can not be seen as a one-time
phenomenon, but must open the way for a cultural change that enables and encourages
a climate of on-going change. In other words, the reengineering effort must prepare the
4

fertile ground for organizational structures and processes that allow the company to
continuously adapt to changing environmental conditions.
Communicate, communicate, communicate. Communication is a crucial factor, and
must include a communication plan that extends to all stakeholders – employees,
owners, unions, press, communities, etc.
Reengineering approach
BCG uses a three stage process – preparation, transformation, consolidation – where each
of the stages contains several steps. The actual redesign of business processes is
considered as part of the transition management. Top management has a dual role in each
of the steps, firstly setting directions and creating value, secondly to motivating individuals
and creating commitment to change.

Manage transformation
Set objectives
Build and sustain
Redesign
value
Integrate and
Commit and
strategic
validate
deliver
processes
1
2
3
4
Check-points

Figure: BCG reengineering approach
When taking the step between different phases, the project is checked against a set of
conditions of satisfaction. These check-points, or toll-gates, exist to ensure that all necessary
actions have been taken in the previous phases. The different aspects to be considered can
be expressed in the form of questions or statements.1
Check-point 1
Rationale for change. Is the rationale for the change initiative identified and
communicated throughout the organization? The Why? and subsequently How? must be
declared and communicated in a way that makes it understandable to all organizational
members.
Senior management understanding and commitment. Has senior management
accepted its sponsor role and is prepared to support the effort by all necessary means? A

1 In the list of check-points, bold text describes the check-point name given by BCG. The questions
and additional text are comments by the author.
5

large-scale process improvement has to be sponsored and facilitated by senior
management, not only through words, but through action. This includes to back up the
project organization and to actively promote the effort.
Selection of processes. Have the process to be scrutinized been identified and have
the right selection mechanisms been used? The selection of process should be based on
the processes' value adding potential, i.e. that a limited number of high-potential process
is selected first.
How much/long/fast? What is the scope of the project in terms of intention level and
time frame? and Have the necessary resources been allocated in terms of financial and
intellectual resources? A common mistake is to allocate too limited resources to the
change project in terms of people and time. Also, the project objectives must be clearly
set, but must not be unachievable.
Organizational readiness. Is the organization, i.e. the individuals working there,
prepared for the effort and has it been communicated appropriately? When individuals
are taken by surprise, they often react irrationally and defensive, i.e. that barriers are
built, stakes are claimed and the considered threat then creates massive resistance.
Assign the best people. Who are the people being assigned to the project? Is it ensured
that they are knowledgeable, committed to the project and not acting watchdog for other
parts of the organization? In many organizations, managers do not give away their best
people, but those they consider as troublemakers or under-performers. In others, people
are sent to change teams as representatives of the unit they come from and are expected
to guard their unit's or department's interest, instead of committing themselves to the
project.
Check-point 2
Assess existing processes. What are the deficiencies of the current processes, i.e.
where are the performance gaps in terms of time, quality, cost and service? This point
assumes that there are identifiable process existent in the organization, that satisfy the
characteristics outlined in chapter Fehler! Verweisquelle konnte nicht gefunden
werden.. Otherwise, this step also includes the identification of work activities that
conceptually can be grouped into processes.
Customer input and competitive assessment. How are customers perceiving the
organization's ability to perform in terms of time, quality and service? and How is the
organization positioned in relation to its competitors with regard to the critical
performance measures that have been identified? This point includes the external
6

assessment of the company's performance by its customers, but also the process of
benchmarking it against its competitor's performance measures.
Magnitude of opportunities. Which is the intended level of improvement that shall be
achieved through the reengineering initiative and is it relevant and achievable? The
objectives to be defined must satisfy the requirement of being ambitious with respect to
the improvement's order of magnitude, without being unreachable. Stretch targets should
only be used if the necessary elevation of the change process can be ensured.
New process vision. How should the new process work, i.e. how should the business
logic look like, what are the necessary resources and how can the process be designed
with respect to low cycle-time and cost, without compromising the required quality level?
The process vision must include a sketch of the contained activities, required resources
and competencies. If applicable, it should also include a description of the technological
components required. Developing the process vision is an iterative process, where
design prototypes are evaluated and refined.
Determination of major changes required. What are the gaps between the new
process vision and the current process and what are the most important parts to be
changed in order to establish the envisioned process? Mapping the existing process
against the new process vision allows the identification of gaps and the required
measures to be taken in order to establish the envisioned process.
Roadmap for change. What actions must be taken in order to bring about the changes
that have been identified and in what way should these actions be taken? As mentioned
above in the description of BCG's reengineering principles, this roadmap is not a fixed
path, but can be adapted over time, i.e. that it serves as guidance, rather than
prescription.
Check-point 3
New process documentation and validation. Is the new process valid and feasible and
has it been documented? The new process design has to be finally determined and
documented. At this stage, the connections with other process need to be identified and
described, the chosen metrics defined and the required resources determined.
Key people’s concerns addressed. Have the comments of all people being relevant for
implementation and the adequate performance of the new process been gathered and
considered? In order to ensure a smooth and friction-free implementation and
deployment of the new process, the concerns of major stakeholders need to be taken into
account.
7

Support systems consistent with new requirements. Are the process' environmental
conditions sufficiently examined and the results determined? The support systems of a
process - performance metrics, measurement mechanisms, evaluation procedures,
reward system, responsibility structure - need to be defined together with the process and
are included in the description of the targeted future state.
Necessary investments funded. Are the necessary funds for implementation and
investments, e.g. in information technology, available? These consideration should also
include slack resources for handling possible operational disruptions related to the
change process, and must include costs for recruiting, training and education of staff, as
well as for possible lay-offs.
Major barriers removed. Are the concerns of people, resulting in possible resistance,
taken into consideration and are the necessary organizational conditions available for the
implementation and deployment phase? Barriers for change can emerge from insufficient
organizational preconditions, lack of competence in change management and the use of
information technology. However, the most important barrier can be found in the heads of
individuals feeling threatened by the changes to come.
Road-map for action. Have all the necessary preparation steps been taken and can the
implementation phase be initiated? Are the necessary steps of the change process
identified? Change management is crucial to the successful conduct of any process
improvement initiative. At this point the actions to be performed during the
implementation and sub-sequent deployment phase are defined and prepared.
Check-point 4
Positive customer reaction. How are the transition process and resulting process and
structures perceived by customers? The purpose of process improvements efforts is to
deliver increased value to the process' customer and consequently the outcome of the
change effort must be checked again these expectations.
Evidence of customer-oriented focus. Has the customer focus been considered and
improved? There must be clear evidence that customer orientation has been imperative
during the redesign effort and this premise must also hold for the implementation and
outcome of the new process.
Improved decision making. Are decisions made by the right people on the right level in
the organization? In order to improve a business process' ability to deliver value,
decisions must be taken as close to the customer as possible. This is achieved through
8

empowerment of people working in the process, i.e. that decision power must be
transferred to those being responsible for the process outcome.
Business plan aligned with new capabilities. Has the business strategy and
implementation plan been aligned with the organization's improved capabilities? No
process oriented organization can be better than its overall business strategy.
Consequently, strategy and capabilities must be constantly evaluated against each other
in an iterative process. New capabilities make it possible to change strategy and
changing strategies may require the development of new capabilities.
Evidence of improved responsiveness to market changes. Is it evidential, i.e. can it
be clearly shown, that new capabilities have been developed that contribute to improved
environmental responsiveness? Adaptability to changing environmental conditions is one
of the guiding principles in any process improvement effort. At the same time, an extreme
focus on operational efficiency might hamper the organization's ability to respond to
changes in the market place. Consequently, both factors must be considered and
balanced against each other.
Top-down vs. bottom-up
In most of the BPR-related literature, reengineering is described as a top-down approach.
Analysis and design starts with the assuring commitment from senior management,
processes are analyzed and designed from an overarching level to more detailed levels.
BCG follows this general principle, but also points out the necessity of including a bottom-up
approach. Both cycles are run as connected iterations.
Need for change
Communication of
change imperatives
Setting the course
Problem identification
Teams deliver results
Develop processes &
Assemble BPR team
define requirements
Development of plans,
budgets, etc. on basis of
new processes
Engage process teams

Figure: Connected change cycles
Cycle 1 - Top-down
Senior executive agreement on need for change. Senior management agreement and
commitment is not the only, but one of the most critical factors for success. Without this
agreement on the need for change and sponsorship all sub-sequent steps can not gain
the required creditability that is necessary for driving a project successfully.
9

Setting the course. Course-setting means to decide upon the general goals and
directions for the change effort, but does not include detailed plans and procedures.
Assemble reengineering team. The reengineering team must be compiled on the basis
of competence and is responsible and accountable for achieving the defined overall
objectives. The reengineering team must include people with competencies in methods
and tools, change management and organization, but not necessarily with in-depths
knowledge about all operational areas covered by the project.
BPR team engages process teams. Each process is scrutinized by a team assuming
responsibility for a specific process. The process teams are staffed with people covering
the different competence areas covered by the process.
Cycle 1 - Bottom-up
Design teams develop new processes and define requirements. The process design
teams are responsible for designing the general design of the new processes and to
define the performance requirements and propose metrics to be used. The results are
transferred to cycle 2 for the development of more detailed plans, budgets and metrics,
but they also serve as input to the problem identification step of cycle 1.
Identification of problems needing attention. The problem identification step is
informed by the overall process development results in cycle 1 and the results from the
results delivered by the teams being responsible for the detailed design of the processes'
operational characteristics. Identified problems are delivered back to management for
evaluation and, if considered necessary, adjustments of the current process design.
Cycle 2 - Top down
Communication of change imperatives and direction by management.
Communication is, besides commitment and sponsorship, the most important
management contribution to project success. The imperative and direction of the change
effort must be communicated throughout the organization in order to gain understanding
and reduce potential resistance.
Development of plans, budgets, performance metrics etc. on the basis of new
processes. A new process design often makes the existing plans, budgets and
performance metrics obsolete, since they often are designed to fit an hierarchical,
functional organization. Consequently, they must be adapted to an organization based on
processes. This development phase is informed by the general process design step in
cycle 1 and the communicated needs and directions staked out by senior management.
10

Download
Consulting approaches to process improvement Boston Consulting Group

 

 

Your download will begin in a moment.
If it doesn't, click here to try again.

Share Consulting approaches to process improvement Boston Consulting Group to:

Insert your wordpress URL:

example:

http://myblog.wordpress.com/
or
http://myblog.com/

Share Consulting approaches to process improvement Boston Consulting Group as:

From:

To:

Share Consulting approaches to process improvement Boston Consulting Group.

Enter two words as shown below. If you cannot read the words, click the refresh icon.

loading

Share Consulting approaches to process improvement Boston Consulting Group as:

Copy html code above and paste to your web page.

loading