1: You have an Exchange Server 2010 organization that contains two Hub Transport
servers. You need to design a recovery plan for the Hub Transport servers that meets the
following requirements:
.Restores all Windows settings
.Restores all Exchange configurations
.Minimizes administrative effort
What should you include in the plan?
A..Retention of Exchange server computer accounts in Active Directory
.Backup and recovery of Windows system state
.A recovery installation of Exchange Server 2010
B..Retention of Exchange server computer accounts in Active Directory
.Backup and recovery of transport queues.A custom installation of Exchange Server 2010
C..Recovery of Windows system state.Backup and recovery of transport queues.A typical
installation of Exchange Server 2010
D..Backup and recovery of Windows system state.A repair installation of Windows Server
2008.A typical installation of Exchange Server 2010
Answers: A
2: Your company has 10 offices. The offices connect to the Internet by using a WAN link.
The offices connect to each other by using a VPN connection. An Active Directory site
exists for each office. You plan to deploy Exchange Server 2010. Each site will contain two
Exchange Server 2010 servers. You need to recommend the placement of domain
controllers and global catalog servers to meet the following requirements:
.Minimize the number of domain controllers
.Must be able to deliver e-mail messages between users of the same office, if a domain
controller and a WAN link fail simultaneously
What should you recommend?
A.In each site, install two global catalog servers.
B.In each site, install two domain controllers. Enable Universal Group Membership
caching for each site.
C.In each site, install two domain controllers. Create a publishing point for an offline
address list on one Exchange server in each site.
D.In each site, install one domain controller that is configured as a global catalog server.
Exam1pass Help You Pass Any IT Exam
http://www.exam1pass.com
Exam1pass
Easiest way to pass IT exams
Enable Universal Group Membership caching for each site.
Answers: A
3: You have a Microsoft Internet Security and Accelerator (ISA) 2006 server that provides
all Internet access for your company.
You have two Mailbox servers configured in a
database availability group (DAG), two Client Access servers, and two Hub Transport
servers. You need to recommend changes to the environment to ensure that users can
access Outlook Web App (OWA) from the Internet if any single server fails. What should
you recommend?
A.Configure a Client Access server array.
B.Deploy a second ISA server and create an ISA server array.
C.Implement Windows Network Load Balancing for the Client Access servers.
D.Deploy two Edge Transport servers that are configured to use EdgeSync
synchronization.
Answers: B
4: Your network contains an internal network and a perimeter network. The internal
network contains a single Active Directory site. The perimeter network contains two
Exchange Server 2010 Edge Transport servers. You plan to deploy an Exchange Server
2010 organization on the internal network. You need to plan the deployment of Hub
Transport server roles to meet the following requirements:
.If a single Hub Transport server fails, e-mail messages from the Internet must be
delivered to the Mailbox servers.
.If a single Hub Transport server fails, users must be able to send e-mail messages to
other users that have mailboxes on the same Mailbox server. What should you include in
the plan?
A.Deploy one Edge Transport server on the internal network, and then configure
EdgeSync synchronization.
B.Deploy one Hub Transport server on the internal network, and then configure EdgeSync
synchronization.
C.Deploy one Hub Transport server on the internal network and one Hub Transport server
on the perimeter network.
D.Deploy two Hub Transport servers on the internal network.
Answers: D
Exam1pass Help You Pass Any IT Exam
http://www.exam1pass.com
Exam1pass
Easiest way to pass IT exams
5: You have an Exchange Server 2010 organization. You need to recommend a client
access solution that meets the following requirements:
.Reduces the time required for users to reconnect to user mailboxes if a single Client
Access server fails
.Prevents users from being prompted for authentication if a single Client Access server
fails
What should you recommend?
A.Client Access server array and hardware load-balancer
B.database availability group (DAG) and hardware load-balancer
C.failover clustering and database availability group (DAG)
D.Windows Network Load Balancing and failover clustering
Answers: A
6: Your company has two data centers. Each data center contains a perimeter network.
Your network contains an Exchange Server 2010 organization. You plan to deploy
Exchange Server 2010 Edge Transport servers in the perimeter networks. You need to
recommend a solution for the Edge Transport servers that meets the following
requirements:
.Distribute inbound e-mail messages across all Edge Transport servers
.Ensure that users receive inbound e-mail messages if an Edge Transport server fails
.Ensure that users receive inbound e-mail messages if a single data center network
becomes unavailable
.Minimize costs What should you recommend?
A.In each perimeter network, deploy one Edge Transport server. Implement failover
clustering.
B.In each perimeter network, deploy two Edge Transport servers. Implement failover
clustering.
C.In each perimeter network, deploy one Edge Transport server. Configure a mail
exchange (MX) record for each server.
D.In each perimeter network, deploy two Edge Transport servers. Configure a mail
exchange (MX) record for each server.
Answers: C
Exam1pass Help You Pass Any IT Exam
http://www.exam1pass.com
Exam1pass
Easiest way to pass IT exams
7: You have an Exchange Server 2010 organization. The organization contains a Mailbox
server named Server1. Server1 hosts two mailbox databases and one public folder
database. You plan to deploy a new Mailbox server named Server2. You need to
recommend a high-availability solution for Server1 that meets the following requirements:
.Mailboxes and public folders must be available if a single Mailbox server fails
.Deploy the minimum number of servers
What should you recommend?
A.Install failover clustering on both servers, and then configure cluster continuous
replication (CCR). Replicate all public folders to Server2.
B.Create and configure a database availability group (DAG). Add Server1 and Server2 to
the DAG. Create database copies. Replicate all public folders to Server2.
C.Create and configure a database availability group (DAG). Add Server1 and Server2 to
the DAG. Deploy a new server named Server3. Create database copies. Configure
Server3 as a dedicated public folder server.
D.Install failover clustering on both servers, and then configure a single copy cluster
(SCC). Deploy a new server named Server3. Configure Server3 as a dedicated public
folder server.
Answers: B
8: Your network consists of a single Active Directory site.
You plan to deploy Exchange
Server 2010.
You need to plan the deployment of Exchange Server 2010 servers to
meet the following requirements:
.All Mailbox servers must belong to a database availability group (DAG)
.MAPI connections from Outlook clients must be load balanced by using a hardware load
balancer
.If a single server fails, users must continue to send and receive e-mail
.The plan must minimize the number of servers deployed
What should you include in the plan?
A.Deploy two servers. On the two servers, deploy the Mailbox server role, the Client
Access server role, and the Hub Transport server role. Configure a Client Access server
array.
B.Deploy two servers. On the two servers, deploy the Mailbox server role, the Client
Access Server role, and the Hub Transport server role. Enable Outlook Anywhere on both
Client Access servers.
Exam1pass Help You Pass Any IT Exam
http://www.exam1pass.com
Exam1pass
Easiest way to pass IT exams
C.Deploy four servers. On two of the servers, deploy the Mailbox server role and the Hub
Transport server role. On the other two servers, deploy the Client Access server role.
Configure a Client Access server array.
D.Deploy four servers. On two of the servers, deploy the Mailbox server role. On the other
two servers, deploy the Client Access server role and the Hub Transport server role.
Enable Outlook Anywhere on both Client Access servers.
Answers: A
9: Your company has an Active Directory forest. The forest contains two sites named Site1
and Site2. You plan to deploy Exchange Server 2010 servers in both sites. You need to
plan a high-availability solution for the Mailbox servers that meets the following
requirements:
.Users must be able to access their mailboxes if a single server fails
.Users must be able to access their mailboxes remotely if a single site becomes
unavailable
What should you do?
A.Deploy two Mailbox servers in each site. Install and configure continuous cluster
replication (CCR).
B.Deploy one Mailbox server in Site1 and one Mailbox server in Site2. Install and
configure continuous cluster replication (CCR).
C.Deploy two Mailbox servers in each site. Create one database availability group (DAG)
named DAG1. Add all Mailbox servers to DAG1.
D.Deploy two Mailbox servers in each site. Create two database availability groups (DAGs)
named DAG1 and DAG2. Add the Mailbox servers from Site1 to DAG1 and the Mailbox
servers from Site2 to DAG2.
Answers: C
10: You have an Exchange Server 2010 organization. The network contains an Exchange
Server 2010 Mailbox server named Server1. All mailboxes are stored on Server1. You
perform a Typical installation of Exchange Server 2010 on a new server named Server2.
You plan to implement redundancy for mailbox access.
You need to recommend a
solution that ensures that client computers can reconnect to their mailbox within five
minutes if Server1 fails. What should you recommend?
A.Configure cluster continuous replication (CCR). Implement a file share witness.
Exam1pass Help You Pass Any IT Exam
http://www.exam1pass.com
Exam1pass
Easiest way to pass IT exams
B.Configure a Network Load Balancing cluster that includes Server1 and Server2.
Implement Active Directory-integrated DNS zones.
C.Configure a database availability group (DAG) that includes Server1 and Server2. Set
the time to live (TTL) for the DNS record.
D.Configure a database availability group (DAG) that includes Server1 and Server2. Use
the same certificate for both servers.
Answers: C